Search: 2015
Results
Clayton B. Wire Playfield Storm Drainage (Summer 2015)
Start Date: May 15, 2015
Estimated Completed Date: August 28, 2015
Project Info:
- Project Manager: Chris Zunino; (916) 264-4075 Ext: 1022
- Architect: HMR
- Contractor: Roebbelen
- Funding Source: Emergency Repair Program
Construction Description: Storm drainage repair
Edward Kelly Preschool Fire Alarm Upgrade
Start Date: May 1, 2015
Estimated Completion Date: August 28, 2015
Project Info:
- Project Manager: Lori Rubenstein
- Architect: HMC
- Contractor: Studebaker Brown
- Funding Source: Measure Q
Construction Description: Fire alarm upgrade
Sacramento High AC Paving at North Parking Lot
Start Date: May 10, 2015
Target Date: August 28, 2015
Project Info:
- Project Manager: Anthony Lea; (916) 264-4075 Ext: 3616
- Architect: HMR
- Contractor: XL Construction
- Funding Source: Emergency Repair Program
Construction Description: Paving at North parking lot
Maple Fire Alarm Upgrade – Preschool
Start Date: June 12, 2015
Estimated Completion Date: August 15, 2015
Project Info:
- Project Manager: Anthony Lea; (916) 264-4075 Ext: 3616
- Architect: HMC
- Funding Source: Measure Q
Construction Description: New fire alarm system upgrade – Preschool
Matsuyama LED Lighting
Start Date: October 9, 2014
Estimated Completion Date: August 28, 2015
Project Info:
- Project Manager: Anthony Lea; (916) 264-4075 Ext: 3616
- Funding Source: Project Green
Construction Description: LED lighting in student restrooms
Nutrition Services Fresh Produce
RFP # 150701
Notice to Bidders
The Â鶹¹ú²úAV is requesting bids from providers of Fresh Produce to provide service for the District’s Fresh Produce Program.
RFP’s must be received prior to 10:01 A.M., on July 23, 2015. RFP’s must be submitted in a sealed envelope, marked with the Bid number and title, and returned to Sacramento City Unified School District, Purchasing Services, 3051 Redding Ave., Sacramento, CA 95820.